Milestones
| 2010 | Established Local Company to increase operations in Abu Dhabi
Commissioning and maintenance contract for Oil & Gas system in Qatar
Turnkey control and instrumentation system for cattle feed plant in India
|
| 2009 | Turnkey Contract for Design,Installation and Commissioning of Instrumentation & Control system for MBR Sewage
Treatment Plants in Oman
Engineering of Visualization and logics for control system for Oil Pipeline in Middle East
Member of Automation Alliance Group
|
| 2008 | Turnkey Contract for Design, Development, Installation and Commissioning of Instrumentation & Control system for waste water treatment plant including networking, telemetry, CCTV and CMMS, in Kuwait
Control and safety system, Fuel Farm for New Doha International Airport, Qatar
|
| 2007 | Turnkey contract for design, development and installation of control system for Dubai Health Care City District Cooling Plant
Control and visualization systems, Cargo Complex for Bangalore and Hyderabad International airports
|
| 2006 | Commenced Kuwait and Qatar Operations
Member of Control System Integrators Association, USA
|
| 2005 | Commenced US operations
Commissioning support of baggage handling control systems in Detroit, Miami and Los Angeles Airports
|
| 2004 | F&G and Triconex Triple Module Redundancy systems for Qatar offshore platforms PS2/PS3 for Qatar Petroleum |
| 2003 | Appointed as System Integrator for F&G of Zellweger Analytics, Dubai
Commenced operations in Singapore
First PCS7 installation in India for biomass based power plant |
| 2002 | Commenced operations in Dubai for DCS and ESD System for Degassing Plant |
| 2001 | Turnkey Electrical systems for 4 Biomass based Power Projects in India |
| 2000 | Large drive line system for Paper Plant in India |
| 1999 | Batching Plant for Poultry Feed Manufacture in India |
| 1998 | Sand Plant control for DISA Foundry in India |
| 1997 | 500+ Control Projects for Carding Machines in Textile Industry |
| 1996 | Total Control System for a large Cattle Feed Plant, India |
| 1995 | Automated Baggage Handling Plant for Changi Airport, Singapore. |
| 1994 | Multiple Special Purpose Machines Control systems for MICO India. |
| 1993 | Introduced automation to MRF Tyres - Calendar Line control |
| 1992 | WareHouse Automation System with ASRS,SCADA and MIS for Textile Plant in Thailand |
| 1991 | Integrated Foundry Automation System including remote connectivity for monitoring |
| 1990 | Executed First Wind Energy Project, India |
| 1986 | Started as First System Integrator of Siemens in India |